In short. Ukrainian law no longer has a “declaration on the beginning of construction works”: Law No. 1817-VIII of 17.01.2017 replaced it with a notification. The notification is filed for consequence class CC1 objects and houses built under a building passport; works start after filing. CC2 and CC3 objects need a permit, issued free within 10 working days.

Message on TelegramWhatsApp

Updated 30.10.2026 · checked against Art. 34, Art. 36, Art. 37, Art. 27, Art. 32 and Art. 39 of the Law on Regulation of Urban Development

Declaration or notification: what is filed in 2026

Until 2017 the right to start construction came from registering a declaration with the inspection (for complexity categories I–III). Law No. 1817-VIII of 17.01.2017 moved to consequence classes CC1–CC3 and replaced the declaration with a notification on the beginning of construction works. Old guides about “registering the declaration with DABI within 5 days” no longer apply, and DABI itself was liquidated by Cabinet Resolution No. 218 of 13.03.2020. The document you need depends on the object:

ObjectDocument to start worksLegal basis
Private, garden or country house up to two floors (attic excluded) and up to 500 m², outbuildings, a garage on a household plotbuilding passport + notification on the beginning of construction worksArt. 27, Art. 34(1)(1)
Other consequence class CC1 objectsdesign documentation + notificationArt. 34(1)(1), Art. 36
CC2 and CC3 objects and objects subject to environmental impact assessmentconstruction works permit from the architectural and construction control bodyArt. 34(1)(3), Art. 37
Works on the Cabinet’s list that need no documentsno document; the object is not commissionedArt. 34(2)

The notification and the permit remain valid until construction is completed (Art. 34(2)). For a CC1 object the law requires no other permit-type documents to start works (Art. 36(2)).

Building plot at the start of construction: a foundation pit with formwork, a mini excavator, bricks, drawings on a table and an information board
By the time machinery enters the plot, the land documents and the consequence class have been checked and the notification filed.

Is your object CC1?

The consequence class is set in the design documentation under building codes (Art. 32). The law does not allow the following to be CC1:

  • objects where more than 50 people will stay permanently or more than 100 periodically;
  • residential buildings above four floors;
  • cultural heritage monuments and new construction in a monument’s protection zone;
  • high-hazard facilities of classes 1 and 2;
  • objects subject to environmental impact assessment.

In Lviv, with its historic centre, we first check whether the plot lies in a monument’s protection zone: new construction there cannot be CC1, and a permit is needed instead of a notification.

Message on TelegramWhatsApp

How the notification is filed

The notification is filed on the form approved by the Cabinet of Ministers (Procedure for construction works, Resolution No. 466) with the state architectural and construction control body where the object is located: electronically in the Unified State Electronic System for Construction (login via Diia with a qualified e-signature) or on paper through an administrative services centre (TsNAP). If the object includes future real estate units, the notification states the registration number of the design documentation in the Register of Construction Activity (Art. 36(1)).

Foreign owners and companies

The customer may be a foreign individual or a company. Documents are signed with a qualified e-signature or filed by a representative under a power of attorney; land rights must be registered in Ukraine. We act as your local representative, file the notification and report changes during construction.

What to prepare

Land documents

Title or lease to the plot or a superficies agreement, cadastral number. The land use purpose must match what you build.

Planning part

Building passport (issued free of charge within 10 working days, Art. 27) or planning conditions and restrictions with design documentation.

Construction participants

Details of the general contractor or contractor and of the persons doing technical and author supervision.

Customer

Details of the individual or company, a qualified e-signature or a power of attorney for a representative.

Cost and timing

WhatAmountTiming and basis
Zakon Lviv support: review, preparation and filingon requestdepends on whether the design and land documents are ready; we quote after reviewing them
Building passportfree10 working days from application, Art. 27
Construction works permit (CC2, CC3)free10 working days from registration of the application, Art. 37(2)
Declaration of readiness of a CC1 object for operationfree10 working days from registration, Art. 39(1)
Lawyer consultation€10030 minutes online, before any work

In our experience, preparation takes the longest: the building passport or design and putting land documents in order. Once the package is ready, filing the notification takes one working day.

After filing: changes and commissioning

  • A new customer, contractor, technical or author supervisor, or an adjusted design must be reported to the control body within three working days (Art. 36(6)).
  • Construction without a filed notification is prohibited (Art. 36(2)).
  • A finished CC1 object is commissioned by registering a declaration of readiness for operation (Art. 39(1)) — the declaration that still exists in the law.
  • Before commissioning, the customer arranges a control geodetic survey by a certified surveying engineer (Art. 39).

Frequently asked questions

Does the declaration on the beginning of construction works still exist in Ukraine?
No. Law No. 1817-VIII of 17.01.2017 replaced it with a notification on the beginning of construction works (Arts. 34 and 36 of the Law on Regulation of Urban Development). A declaration remains only at the end: the declaration of readiness of a CC1 object for operation.
Do I need a building permit for a private house?
Not for CC1 objects or houses under a building passport: a notification is enough. A construction works permit is required for CC2, CC3 and objects subject to environmental impact assessment; it is issued free of charge within 10 working days (Art. 37).
How much does it cost?
Zakon Lviv support is priced on request after we review the land documents and design. The building passport, the construction permit and registration of the readiness declaration are free by law (Arts. 27, 37, 39). A 30-minute online consultation costs €100.
Can a foreigner or a foreign company file the notification?
Yes, as the customer of construction, with a qualified e-signature or through a representative acting under a power of attorney. Rights to the land plot must be registered in Ukraine.
Where is the notification filed in Lviv?
With the state architectural and construction control body where the object is located, electronically via the construction e-system (login through Diia with a qualified e-signature) or on paper through an administrative services centre.
Can I build under a notification in Lviv’s historic centre?
New construction in a cultural heritage monument’s protection zone cannot be CC1 (Art. 32), so a construction works permit is needed. We check this before preparing documents.

Planning construction or reconstruction in Ukraine?

Send us the plot address and what you build. A lawyer will tell you whether a notification is enough or a permit is needed, and quote price and timing.

Message on TelegramWhatsApp
If you find an error or inaccuracy in the text, select it and press Ctrl + Enter

Consultation of a lawyer

For a detailed consultation with a senior lawyer, message us on Telegram, Viber or WhatsApp or request a call back using the form:

Why choose us

  • Turnkey, no legwork for you

    We take on the whole matter: documents, filings, queries from the authorities. You make the decisions and sign; most steps are handled remotely, and we contact you only when it matters.

  • Personal involvement in every case

    An experienced lawyer handles your matter personally, backed by the group's practice in 50+ countries. Where you hear “it can’t be done”, we look for a lawful way.

  • Your affairs stay yours

    Information about you, your company and your deals reaches neither competitors nor third parties. We disclose only what the law or the procedure requires, and the contract says so.

  • We fight red tape at no extra cost

    Refusals, objections, delays: we respond, revise and appeal until the matter is closed.

  • Faster and sharper, right first time

    Full involvement and 14 years of experience let us get right the first time what takes some firms three attempts.

  • We see it through

    The same lawyer stays on your matter even when it takes months. When an accredited partner handles a stage, we remain accountable to you.